Lowe’s Companies Rail Infrastructure Improvements
Rehabilitating and rebuilding rail access to keep a major distribution facility’s unloading operations running smoothly.
Project Highlights
- Rehabilitated more than 2,100 feet of existing industrial lead track
- Designed a new No. 8 turnout connection to support facility rail operations
- Constructed new ballast and embedded track sections using 115-pound rail
- Included approximately 1,000 feet of new industry track infrastructure
- Incorporated precast concrete rail crossings for facility circulation
- Coordinated track design with drainage systems, utility crossings, and fire access routes
- Designed embedded track adjacent to active loading and unloading areas
- Produced construction-ready engineering plans for railroad and site integration
- Coordinated design requirements with CSX operating standards and infrastructure

Project Details
Via Rail Engineering provided railroad engineering and design services for rail infrastructure improvements at the Lowe’s distribution facility in Palmetto, Georgia. Located along the CSX A&WP Subdivision, the project was developed to improve rail access within the facility while supporting ongoing distribution and unloading operations.
The project included rehabilitation of existing industrial trackage, realignment of portions of the lead track, and construction of a new industry track connection designed to serve facility operations. Improvements included a new No. 8 turnout, track extensions, embedded track sections adjacent to loading areas, bumping post installation, and modifications to existing track geometry to accommodate site requirements.
In addition to track infrastructure improvements, the project required coordination with facility access routes, grade crossing enhancements, drainage systems, utility crossings, fire access areas, and site development features. The design incorporated precast concrete rail crossings, embedded track construction, drainage accommodations, and utility protection measures to integrate railroad infrastructure with the active industrial site.
Via Rail Engineering developed construction-ready plans and specifications that coordinated railroad requirements, facility operations, and site infrastructure while maintaining connectivity to the CSX network. The resulting design provides a comprehensive rail-serving solution tailored to the operational needs of the distribution facility.
LOCATION: PALMETTO, GEORGIA
Services Used:
- Industrial Rail Design
- Railroad Coordination
- Track Rehabilitation Design
- Track Expansion Design
- Grade Crossing Design
- Rail Facility Planning
- Construction Documentation